Activity partitions are used in hotels and shopping malls. Due to the wide application of movable partitions, its installation process has also received much attention. How to install the activity partitions, the following small series will introduce you!
First, the tracking system:
1. As shown on the paper, check the rails that are assembled on the floor in sequence before the partition is installed.
2. Mark the track line and place the bracket at the specific location.
3. Install the rail bracket to the ceiling.
4. Check that the moving partition is firmly fixed to the rail. The rails and brackets must be stored loosely in the storage area so that the bracket plates can be moved to other locations.
5. Finally, the proper position of the storage track is measured before adjusting the facilities of the main track. This is very important for intersection placement.
Second, the installation of track facilities:
1. When the partition hangs on the track, the escape exit track can be removed without rebuilding the crane.
2. For the escape exit track must be a special bracket track connection.
3. When installing the rail, it is necessary to carry out the construction according to the accurate data of the adjustment at the time of measurement.
Third, the track adjustment:
1. Remember that the track is loose enough above all the brackets. Guarantee track pause time.
2. Tighten all the track connections and adjust the track level correctly. The track installation direction must also be horizontally straight.
3. For the installation of track facilities, the sound insulation and mineral wool are the necessary plates for installation.
4. There are “Lâ€, “T†and “Ten†dams for the track, which are used for the connection of the steering. It is generally not recommended to use the “ten†vent. L and T are trimmed to the appropriate size and are numbered to indicate their position.
Fourth, feasible wall panels:
1. Open the escape exit track;
2. According to the tracking system, remember to fix it on the track in the correct order.
3. Adjust the height of the carrier before closing the moving partition, check the straight angle of the track, so that the track partition can run well.
4. Check the vertical condition of all partitions. If there is no damage, it can enter the edge of the rubber frame of the rubber seal vertically and there is no bending (if the connection is not suitable, otherwise).
5. If the orbital direction is horizontal, but the partition is suspended, the carrier height must be adjusted.
6. Clockwise = partition rise, turn left = partition sink;
7. Remember that the height is good. Tighten the socket of the carrier threading, adjust the partition and open the rail when it is well, and adjust the width of the door shape.